Wandering River Tank Foundations

Wandering river
Wandering river 2

Project Description:

CWP’s scope of work consisted of the construction of two 2 m tall octagonal tank foundations. Each of the 250 m3 foundations were designed to hold evaporator tanks for the Blackrod SAGD facility. This project also included setting cast in place anchor bolts and cold weather concrete curing.

  Job Duration: November 2023 – December 2023

Keyera South Cheecham Sulphur Handling Facility 

Keyera3
Keyera4

Project Description:

The scope of work for this project consisted of new concrete construction for the facility. The early concrete works for the facility included two octagon shaped tank foundations, two concrete pit structures, a retaining wall and a building foundation. In total 1,060 m3 of concrete and 200,000 kg of rebar were placed for these structures.

  Job Duration: April 2021 – August 2021

Fox Creek Expansion Project

IMG_9297
Fox Creek

Project Description:

This project consisted of the construction of two new concrete octagon shaped foundations. These foundations received 110 concrete pedestals consisting of 470 anchor bolt assemblies. In addition to the silo foundations, the contract also consisted of multiple smaller foundations for the new conveyors and truck scales. In total, 900m3 of concrete were poured and cured during the cold winter temperatures.

  Job Duration: Jan 2019 – March 2019

Enbridge Cheecham Foundations

Enbridge Foundations
Enbridge Foundations

  Job Duration: July 2015 – December 2015

  Total Job Value: $0.7M

Gibsons Edmonton South Terminal Expansion Foundations

Gibsons Edmonton South Terminal Expansion Foundations
Gibsons Edmonton South Terminal Expansion Foundations

Project Description:

CWP’s scope of work included 350m3 of cast-in place concrete and associated formwork for foundations and piles for Gibsons Energy at their South Terminal facility in Edmonton, AB. Work included ground prep, erect/strip formwork, reinforcement, pour/place concrete and setting anchor bolts.

  Job Duration: July 2014 – November 2014

  Total Job Value: $0.5M

Cenovus Energy – Loading Dock

  Job Duration: October 2013 – July 2014

  Total Job Value: $1M

Cenovus Energy – Roof Retrofit

  Job Duration: August 2013 – June 2014

  Total Job Value: $1.3M

Cenovus Energy – Birch Creek Camp

  Job Duration: January 2013 – May 2014

  Total Job Value: $1.6M

Cenovus Energy – Elks Point Grading

  Job Duration: September 2013 – December 2013

  Total Job Value: $0.6M

Cenovus Energy – Sunday Creek Bridge

Sunday Creek Bridges Project
Sunday Creek Bridges Project

Project Description:

Rehabilitation of a single span one lane existing bridge and construction of an adjacent single span one lane bridge which acted as main access/egress to the Cenovus Energy plant site at Christina Lake, AB.  Traffic management was paramount throughout construction as the existing bridge was the only way in and out of the plant site in case of emergency.  Scope of work included piling, backfill and compaction, girder erection, precast deck panel installation, road grading on the new bridge.  Rehabilitation of the existing bridge included removal and replacement of timber decking, railing reconstruction, abutment modifications and regrading approaches.

  Job Duration: May 2013 – November 2013

  Total Job Value: $2.9M

Cenovus Energy – Foster Creek Loading Dock

  Job Duration: July 2012 – September 2012

  Total Job Value: $0.3M